Hauxton Active Remediation Complete

Posted on Thursday, 05 January 2012 10:04AM by Steve Edgar
Following 21 months of active remediation and with over 90,000 man-hours worked since excavation commenced, the active remediation phase at the former Bayer Crop Science site has been completed.

During this period over 200,000 tonnes of contaminated soil has been treated and re-used on site and 110 million litres of water (the equivalent of 44 Olympic-sized swimming pools) treated.  The site has now been restored to a development platform but before development commences on the site it will now be monitored for a minimum of six months to assess the remediation works before reports are issued to the Environment Agency and South Cambridgeshire District Council to review in order to allow development to commence.