CASE STUDY: FORMER LANDFILL REMEDIATION

CASE STUDY: FORMER LANDFILL REMEDIATION
Client: Kier Build
Value: £1,200,000
Activities: Physical and biological treatment, earthworks
Brief
To restore and remediate a former landfill site and undertake remedial treatment by ex-situ biological methods.
To provide cut and fill earthworks ensuring an earthworks balance.

Scope of Works
  • Site strip and segregation of re-useable topsoil.
  • Expedited cut and fill earthworks to building footprint to allow the commencement of piling.
  • Cut and fill earthworks to remainder of the site.
  • Nominal 60,000m3
     of contaminated material for handling treatment and re-use.
  • Zero off site disposal (excluding 900 tonnes of U2 Material).
  • Crushing, screening and sorting of soils.
  • Ex-situ biological treatment of soils.
  • Re-use to consultant prepared geotechnical specification.
  • Work due to be completed in a 20 week programme with the subsequent classification of the material as non-hazardous after treatment and replacement under paragraph 19 exemption from waste management licensing.